7th May 2010

Good news!  WISDOM removed their fill!







23rd April 2010

WISDOM are supposedly going to remove the fill, which has diminished in size after relocation.  It has been cordoned off at the top corner near Stream St. We'll see.








9th April 2010

Peter, our Site Supervisor sends Jandson Homes pictures showing 2 x dirt pile fills that need to be cleared before they go-ahead. Apparently, according to a home forum and Jandson, this is a problem especially with new estates. Our best guess is that WISDOM and METRICON building on either side of us have dumped their dirt on our land. HOW RUDE!

I contacted both of their offices requesting that they remove this. The cost from Jandson to us if they removed it on our behalf ranges up to $2,000!

After asking Jandson if they could merely push it to the side. Jandson reply that Chris, the Construction Manager has advised the excavators out on-site to push the spoil to one side so it is out of their way for the time being.


WISDOM Home in background

METRICON Home in background

7 April 2010
Jandson order a Pegout survey for completion by 9th April 2010

30th March 2010
Email from Jandson Homes. The files have now been moved from Contracts to Construction Dpt.
25th March 2010
RAMS post out the Authority to Commence Construction letter. We email a copy of this to Jandson Homes

18th March 2010
Jandson Homes post out
1) a copy of the Council Approved and stampled plans
2) a copy of the Home Owners Warranty Insurance and
3) a copy of the Builders Public LIability and Building Insurance.

We add a copy of the Building contract and post this to RAMS to approve the Authority to Commence Construction.

8th March 2010
DA approval received!